Borkum West II: Original in offshore
The project has been in development for nearly three years, and was originally planned as a 400MW plant consisting of 80 5MW turbines. After the financial crisis, however, Trianel faced difficulty in financing the full amount. The sponsor halved the projects size in November 2009, with the aim of financing the remaining 200MW as a second phase. In December that year, the European Commission awarded the project Eu43 million from the European Energy Programme for Recovery (EEPR).
The European Investment Bank (EIB) and the State Bank of North Rhine-Westphalia (NRW Bank) provided the majority of funding. The four initial lead arrangers, Dexia, Rabobank, KfW and UniCredit, were joined by ASN Bank, SEB, Deutsche Bank, Helaba and NIBC to complete the commercial bank tranche. UniCredit was the documentation and co-ordination bank, Dexia was the modelling bank and KfW was the technical and insurance bank.
The debt facilities for the wind farm total Eu544 million. The development banks are providing Eu456 million of this, through a Eu100 million direct loan and Eu203 million guaranteed facility from the EIB and a Eu153 million guarantee facility from NRW Bank.
The risk guarantees for the EIB facility are Eu50 million from NRW, Eu25 million from Rabobank, Eu24 million each from KfW and UniCredit, Eu22 million from Dexia, Eu18 million each from Deutsche and SEB, Eu15 million from ASN and Eu6.6 million from Helaba. The eight commercial banks also provided the same levels of risk guarantee for the NRW facility.
The commercial tranche is comprised of a Eu16 million term loan, a Eu38.5 million contingent debt facility, Eu14 million letter of credit facility and Eu20 million 3.5-year VAT bridge. The contingent debt facility has Eu5.9 contributions from UniCredit and KfW, Eu5.5 from Dexia, Eu5 million from Rabobank, Eu4.4 million each from Deutsche and SEB, Eu3.9 million from ASN, Eu2 million from NIBC and Eu1.6 million from Helaba. NIBC is providing the term loan, Rabobank the letter of credit facility and KfW the VAT bridge.
The debt has a 15-year tenor with an expected life of 13 years, thanks to the inclusion of cash sweeps. The remaining roughly Eu295 million of the projects cost is funded with equity from Trianel. Trianel is also offering a limited completion guarantee to the lenders.
The farms construction has been contracted to several different entities. Areva has a Eu400 million contract to supply the forty turbines for the project. Dredging Environment & Marine Engineering (DEME) will carry out the pre-piling foundation works and installation of these turbines under a Eu72 million contract. Seeway Heavy Lifting is carrying out the transport and installation of the substation and the 40 tripod jacket foundations. Weserwind and Erndtebrucker Eisenwerke are providing the tripod foundations, and Norddeutsche Seekabelwerke (NSW) is installing the internal farm cabling.
The turbines will be assembled on land, just south of Borkum at Eemshaven, and finished components will be delivered to the site by cargo barge. The turbines will then be erected at sea using cranes.
The wind farm will be located 45km north of the East Fresian island of Borkum, in an area with a 10-year mean wind speed of 9.92m per second. The farm covers a 56km2 area, making it the largest project in the German North Sea, and is adjacent to Germanys first offshore wind project, Alpha Ventus. It is the first wind farm to be supplied with Arevas new M5000 turbines, each with a rotor diameter of 116m. Trial operations will begin in summer 2012, with full operation set to start at the turn of the year 2012/2013. Once this first phase is completed, work will start on the second phase of the project. n
Trianels shareholders are ewmr (Energie- und Wasserversorgung Mittleres Ruhrgebiet, 29.47%), STAWAG Stadtwerke Aachen (14.29%), Stadtwerke Bonn (6.93%), Überlandwerk Fulda (6.49%) Stadtwerke lübeck (6.11%), SWU Energie (4.53%), Stadtwerke Jena-Pößnek (3.57%) Stadtwerke Halle (3.55%), Niederrheinwerke Viersen (3.43%), Salzburg AG für Energie, Verkehr und Telekommunikation (2.1%), enwor (2.04%), Allgäuer Überlandwerk (1.48%), NVB Nordhorner Versorgungsbetriebe (1.42%) Stadtwerke Hamm (1.18%), GSW Gemeinschaftsstadtwerke (0.89%), Regio Energie Solothurn (0.71%), Stadtwerke lünen (0.7%), Energie- und Wasserversorgung Rheine, Energie Wasser Niederrhein GWS Stadtwerke Hameln, Hertener Energiehandelsgesellschaft, Schleswiger Stadtwerke, Stadtwerke Bad Salzuflen, Stadtwerke Dachau, Stadtwerke Elmshorn Stadtwerke Fröndenberg, Stadtwerke Gronau, Stadtwerke Sindelfingen Stadtwerke Tuttlingen (all 0.59%), Stadtwerke Detmold (0.43%), Stadtwerke Flensburg (0.4%), Stadtwerke Unna (0.39%) Stadtwerke EVB Huntetal (0.36%), Stadtwerke lemgo (0.32%), Stadtwerke Schwäbisch Hall (0.31%), Stadtwerke Georgsmarienhütte, Stadtwerke Herford, Stadtwerke lengerich, Stadtwerke Soest, Stadtwerke Verden, and Teutoburger Energie Netzwerk (all 0.3%).
Borkum West II (Phase I)
Status: Closed 17 December 2010
Size: Eu860 million
Location: German North Sea
Description: 200MW offshore wind farm
Sponsor: Trianel
Mandated lead arrangers: UniCredit (Documentation and Co-ordination), Dexia (Modelling), KfW (Technical and Insurance), Rabobank, ASN Bank, SEB, Deutsche Bank, Helaba and NIBC
Non-commercial lenders: EIB and State Bank of North Rhine-Westphalia (NRW Bank)
Sponsor financial adviser: SPF Partners
Sponsor legal adviser: Gorg Rechstanwalte
Commercial lender legal adviser: Linklaters and Hogan Lovells
Multilateral legal adviser: Linklaters
Main contractors: Areva, SHL, NSW, DEME.
Request a Demo
Interested in IJGlobal? Request a demo to discuss a trial with a member of our team. Talk to the team to explore the value of our asset and transaction databases, our market-leading news, league tables and much more.