Asia-Pacific Wind Deal of the Year 2013: Boco Rock


Australia’s incoming federal coalition government has been, as promised, unsupportive of new renewable development. In 2013, it started the process of shutting down the Clean Energy Finance Corporation and reviewing the country’s renewables targets.

Boco Rock Wind Farm Pty Ltd
STATUS
Signed 25 June 2013, financial close 26 June 2013
SIZE
A$361.2 million
DESCRIPTION
Financing for the acquisition and construction of the 113.2MW wind around 35km south of Cooma in New South Wales, Australia
SPONSOR
EGCO
VENDOR
Asia Pacific Renewables Limited
(mostly owned by Continental Wind Partners)
MLAS
ANZ (facility agent, security trustee), BTMU, ICBC, SMBC and Westpac
SPONSOR’S FINANCIAL ADVISER
HSBC
SPONSOR’S LEGAL ADVISER
Baker & McKenzie
VENDOR’S FINANCIAL ADVISER
ANZ
VENDOR’S LEGAL ADVISER
Herbert Smith Freehills
LENDERS’ LEGAL ADVISER
King & Wood Mallesons
ENVIRONMENTAL CONSULTANT
Environ
ENERGY CONSULTANT
Garrad Hassan
TECHNICAL CONSULTANTS
ROAM, GL Hassan, Parsons Brinckerhoff
INSURANCE ADVISER
AON
MODEL AUDITOR
Corality
MARKET CONSULTANT
ACIL Tasman, SKM
ACCOUNTING & TAX ADVISER
PwC
O+M MANAGER
Continental Wind Partners
EPC CONTRACTORS
GE Wind Energy and Downer EDI Engineering Power
OFFTAKER
EnergyAustralia
But foreign interest in existing assets was still strong, as demonstrated by the A$361.2 million ($324 million) financing to support EGCO’s acquisition and the development of the Boco Rock wind farm. Boco Rock was a complex undertaking and included greenfield construction risk. Banks also had to get comfortable with lending to Boco Rock before they knew the identity of its purchaser.

Developer Continental Wind Partners wanted to have in place commitments from banks to finance the project to make sure interested bidders would not be deterred from bidding by the transaction costs. The seller also offered robust operations and maintenance warranties that helped mitigate lender concern. But a developer’s decision to raise the debt for a project before raising its equity is a tweak to the standard project finance checklist.

The deal’s construction risk added a layer of complexity, since any delay in closing on the debt or the equity would have had a knock-on effect on the developer’s ability to complete the project on schedule. Continental Wind wanted to move into construction as quickly as possible, in part because its engineering, procurement and construction contract with General Electric was denominated in euros

The run-up to the elections that returned the coalition led to volatility in the value of the Australian dollar. Lenders, as a result, did not run the final financial models until the day of signing on 25 June. The sponsor made a first draw the following day on the debt, which comprised a single A$251.4 million 5-year term loan from five banks – ANZ, BTMU, ICBC, SMBC and Westpac. The financing also included A$109.8 million in equity.

The fact that EGCO, a Thai generator, won the bidding to buy the asset would have been an unexpected comfort to lenders. Like several South-East Asian sponsors, EGCO has been looking to expand its total installed renewable capacity, and Australia has the most plentiful opportunities and reliable regulatory regime for wind of any regional jurisdiction.

EGCO is understood to have bid for previous Australian assets that came up for sale, including the Hallet 5 wind farm, which was Eurus Energy eventually acquired, as welkl as Hydro Tasmania, on which Guohua Energy, a unit of Shenhua Group, was lender. Boco Rock deal marks the company’s first foray into the Australian renewable market and its first investment outside of South-East Asia.

EGCO’s success will have been particularly welcome to the Japanese banks, since the buyer’s second largest shareholder, after Thai state-owned utility EGAT, is TEPDIA Generating, a joint venture between TEPCO and Mitsubishi Corporation. TEPDIA owns 23.94% of EGCO, and each of its shareholders are important clients of the Japanese lenders.

Australian power is no less immune to political interference, however. The success of the coalition in the 2013 election has effectively led to a moratorium on new offtake agreements. The country’s main utilities, AGL, EnergyAustralia and Origin Energy, are said to be unwilling to sign any new agreements except at tariffs that are not acceptable to sponsors. It may be a while before the Boco Rock deal sparks any imitators.