Latin American Power Deal of the Year 2013: Chaglla
BNDES and the IADB usually take the lead in structuring project financings on which they lend, but for the $773.5 million debt for Odebrechts Chaglla hydro project in Peru, the two shared lead billing. The intercreditor negotiations were, to say the least, protracted.
Empresa de Generación Huallaga |
STATUS |
Signed 5 July 2013 |
SIZE |
$1.2 billion |
DESCRIPTION |
406MW capacity run-of-river hydro project in Huánuco, Peru |
SPONSOR |
Odebrecht |
EQUITY |
$425 million |
DEBT |
$773.5 million |
LENDERS |
BNDES, IADB, Cofide, BBVA, SG, Crédit Agricole, DNB, SMBC, Deutsche Bank |
ADMINISTRATIVE AGENT |
Bank of New York Mellon |
SPONSOR FINANCIAL ADVISER |
BNP Paribas |
SPONSOR LEGAL ADVISER |
White & Case |
BNDES LEGAL ADVISER |
Shearman & Sterling |
IADB LEGAL ADVISER |
Clifford Chance |
DEUTSCHE LEGAL ADVISER |
Milbank, Tweed, Hadley & McCloy |
MARKET CONSULTANT |
Mercados Energéticos Consultores |
TECHNICAL CONSULTANT |
Mott MacDonald |
ENVIRONMENTAL CONSULTANT |
ERM |
HYDROLOGY CONSULTANT |
DHI |
WATER QUALITY CONSULTANT |
JGP Consultoria |
Chaglla did not need to close on a long-term debt package immediately, but Odebrecht did not expect that the financing would take until 5 July 2013 to sign.
Odebrecht had not planned to use BNDES funding for Chaglla. In early 2011, about 15 commercial lenders expressed interest in the deal, some of them with large underwriting commitments. But the eurozone crisis deepened, and some European lenders retreated from Latin American project finance. Odebrecht decided that ECA debt might be needed to complement an IADB-structured A/B loan. BNDES was soon attached to the financing, because of the presence of Odebrecht, a large Brazilian contractor and sponsor.
The lenders and Odebrecht then had to determine debt sizing for the project. But Chaglla has an uncommon merchant nature, which encouraged the diverging views on the gearing. Chaglla has a nameplate capacity of 406MW, but only in Huánucos wet season, and 284MW as an annual average. It is contracted to sell its production at 284MW to state utility Electroperú, under a 15-year offtake agreement.
But the project will probably operate at a capacity of less than 284MW in the dry season. So, Chaglla may have to buy electricity on the spot market during dry stretches to meet its obligations under its PPA.
Odebrecht declined to offer a full construction guarantee for project company Empresa de Generación Huallaga. BNDES prefers to lend against construction guarantees, and such guarantees tend to feature in its project financings. But Odebrecht convinced lenders to share the risk.
Odebrecht sought gearing of 70%, while the banks preferred a lower level. Sponsor and lenders settled on 65%, sized off a P95 hydrology scenario, with Odebrecht contributing $425 million in equity.
But BNDES and the IADB still had to resolve inter-creditor issues, and complete all of the projects documentation, included addressing easements for an accompanying 127.5km 220kV transmission line. Odebrecht, in the meantime, closed two additional bridge loans to help it keep the plant in construction. SMBC and DNB joined BBVA, BNP and SG in the two later bridge loans, which were essentially parallel to the original bridge.
BNDES ultimately committed to provide a $340 million direct loan to Chaglla. The IADBs A/B loan, meanwhile, assured Chaglla $333.5 million. The IADB agreed to provide a $150 million toward the A tranche, while commercial lenders would split a $183.5 million B piece. Cofide would fund a separate Deutsche Bank-led $100 million loan. The B loan has the shortest tenor it matures in 2030, a year before the rest of the debt financing. BBVA and SG were mandated lead arrangers on the B loan, while Crédit Agricole, DNB and SMBC participated. BNP did not participate in the long-term deal.
Odebrecht expects that Chaglla will be operational in 2016. At that point, the plant could represent up to 15% of Perus national energy demand. The project will comprise a 202-meter concrete face rock-filled dam, a 1,124-meter diversion tunnel, and a powerhouse.
Request a Demo
Interested in IJGlobal? Request a demo to discuss a trial with a member of our team. Talk to the team to explore the value of our asset and transaction databases, our market-leading news, league tables and much more.